TORONTO RUNWAY
        Delcan has reported on its project management role in the
        construction of a four lane vehicle access to the new infield
        development at Pearson International Airport in Toronto which passes
        beneath runway 15L-33R and the most heavily used taxiways at the site.
        The design phase of the project began in late 1997 and the construction
        of the approaches to the eastern end of the tunnel from the airport
        apron road was tendered for $7 million and completed in November, 1998.
        Meantime, the final design of the main tunnel and western approach was
        completed in August, 1998.
        This is a four lane divided vehicle corridor, 26 m wide, 7.4m high
        and just over half a kilometer long. Armbro Construction won the $38
        million contract for the tunnel and western approach works which are
        scheduled for completion in May, 2000. The team of Morrison Herschfield,
        Acres and Delcan, within the project management consortium which
        includes Sverdrup Civil and Maunder Britnell, is providing the resident
        engineering and construction administration services to the Greater
        Toronto Airports Authority as client.
        The tunnel, which one of only a handful of similar facilities in
        North America, will allow unimpeded access to the new infield
        development, which in turn will permit redevelopment of the existing
        Terminals 1 and 2 into a single new terminal.
        World Tunnelling, August 1999
        SIR ADAM BECK PROJECT ON HOLD
        The Sir Adam Beck project in Ontario has not been canceled, but is
        "on hold" until reorganization of the electricity industry in
        that province is completed. According to Ontario Power Generation
        management, reorganization caused by the change from monopoly to open
        competitive market is expected to take at least six months, and that the
        project will commence within two years. The likelihood of project
        cancellation is "extremely low", and re-tendering of the
        contract is not planned.
        The project, whose contract was awarded in 1998 to the Obayashi/Kenaidan
        JV, consists of a 10 km long, 14 m diameter tunnel which will divert
        part of the Niagara River to the existing Sir Adam Beck power station.
        The tunnel passes through limestone and shale, and requires a
        double-gripper machine that is able to push off of the precast concrete
        segmental lining. The machine will start at the power station site and
        bore uphill, breaking through at the intake structure. The intake will
        be built within a cofferdam located in the middle of the river.
        The design-build project is estimated to cost CAD $400 Million, with
        bid design and contract documentation prepared by the consulting Joint
        Venture of Acres/Bechtel/Hatch Mott MacDonald. Harza Engineering of
        Chicago will act as consultant to the Obayashi/Kenaidan JV, with
        sub-consultant services provided by
 Parsons
        Brinckerhoff of New York.
        Tunnels and Tunnelling International, November 1999
        ASTM TRENCHLESS TECHNOLOGY STANDARDS
        The American Society for Testing and Materials (ASTM) has recently
        announced the publication of "ASTM Standards Related to Trenchless
        Technology".
        This document compiles 78 standards pertaining to pipe materials and
        rehabilitation methods used in trenchless construction, including the
        latest standards on concrete pipe, vitrified clay pipe, fiberglass pipe,
        steel pipe, ductile iron pipe, glass reinforced concrete pipe, PVC pipe
        and polyethylene pipe. For more information, visit ASTM's Web site at
        www.astm.org.
        Trenchless Technology, December 1999